Long Thanh airport timetable faces review as safety conditions remain

The investor has sought a phase 1 extension to 2027-28 after reporting that component project 3 cannot meet its 2026 deadline.

By Sari Wulandari

Airport construction site with unfinished terminal buildings and access roads
Photo: Tuoi Tre News

Vietnam’s Long Thanh airport can begin operating only when all conditions are satisfied and absolute safety is assured, Standing Deputy Prime Minister Pham Gia Tuc said. His direction followed confirmation from investor Airports Corporation of Vietnam (ACV) that component project 3 at the Dong Nai City airport would not be completed in 2026.

ACV proposed putting the Ministry of Construction in charge of a review covering every component project, followed by a proposal to extend implementation of phase 1 to 2027-28. Tuc instructed ACV to establish deadlines for unfinished work, installation and testing, and determine the earliest feasible opening.

The investor reported equipment and materials that differed from contractual specifications, with purchasing and installation occurring before changes received approval. It also identified completed work based on drawings inconsistent with approved designs, and construction undertaken without approved drawings. ACV said these problems must be resolved before the works could be accepted and operations authorised.

ACV must provide its findings to the government and construction ministry within a week of the meeting. The ministry’s progress assessment is due before December 10, ahead of consideration by competent authorities of investment-policy changes.

Vietnam Airlines and Vietjet said their preparations followed approved plans, but cautioned that operating alongside construction could affect safety and service standards. Vietnam Airlines also stressed the preparation time required for international services, for which bookings are often made months ahead.

Road connections remain unfinished. The construction ministry said several expressway stretches and the An Phu interchange were expected to be substantially complete in early Q2-2027. It called for faster work and contingency arrangements to address disruption or traffic volumes beyond available capacity.